Engineers are covered by mechanic’s liens but only on private projects. An owner must file a “notice of contract” signed by him and the general contractor before commencing work. The lien must be filed within 60 days of notice of termination or completion of services. For a subcontractor, the time limit is 30 days. An action to enforce a lien must be filed with one year of filing the lien. R.S. 9:4807
Disclaimer: Louisiana may
Commercial Collection Topics
- Indiana Commercial and industrial projects do not require a pre-lien notice in Indiana. Those wishing to acquire a lien ...
- Alaska A pre-lien notice is not required but recommended to make enforcement easier. A lien can be filed by any person...
- Arkansas A notice of intent to file a lien is required at least 10 days before filing a lien. Arkansas permits...
- District of Columbia No pre-lien notice is necessary. DC Code allows general contractors who have supplied labor or materials for the erection improvement,...
Related Terms: