No notice prior to commencement of the work is necessary. Engineers can file a lien as long as construction has commenced. If a project is never started,
The lien must be filed within 4 months after last furnishing services. A subcontractor must file within 3 months. To bring an action in court it must be brought within one year of filing the lien statement. Kansas does permit
Disclaimer: Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.