Engineers are entitled to liens. Unlike most other states before you can file a lien you must get a permit from the court. A hearing is then held to determine whether you can move forward with your claim. For a design professional to have a claim some work must be started on the project. If a notice of completion has been filed you have 45 days proceed. If no notice of completion then one year and 45 days.
Disclaimer
Commercial Collection Topics
- Arkansas A notice of intent to file a lien is required at least 10 days before filing a lien. Arkansas permits...
- California California Lien Law says to preserve mechanics lien rights a preliminary notice must be filed within 20 days of the...
- Arizona Unlike many states, Arizona requires all claimants – contractors or subs - to file a pre-lien notice no later than...
- Alabama Contractors or subs who do not have a direct contract with the owner must file a pre-lien notice before they...
Related Terms: